aak7
Petroleum
- Apr 15, 2012
- 6
Hi,
I am new here and need some guidance.
A new pump skid needs to be fabricated and fitted in a ready location at my gas platform. From what I heard, the old pump never worked - did not know a lot of details. Did a calculation to determine if NPSHa > NPSHr so there won't be repeat incidents. (suspect pump didn't work because of cavitation).
This pump skid is for well equalization purpose. Liquid service is diesel, from a 2000L tank, routed through a long piping to a pump (2 decks down), to be pumped to individual well to equalize the SCSSV.
I considered pressure of the tank (which is atmospheric), static head (fluid elevation from tank to pump suction), friction loss and acceleration head. from calculation, if taking into account the acceleration head, NPSHa will be < NPSHr, which mean that heavy cavitation occurs.
Acceleration head, Ha, formula I used:
Ha = LVNC/gk, where
L=actual suction pipe length (metres)
V=mean flow velocity in suction line (m/s)
N=pump speed (rpm)
C=pump constant factor. I used C=0.016
g=9.81 m/s2
k=liquid factor (a constant)
I want to explore ways to resolve the acceleration head loss issue, to ensure NPSHa > NPSHr. Options:
1. Reduce actual suction pipe length, L by reroute whole piping to make it shorter/more straightforward between pump suction and tank. But this will be a tremendous work, possibility of welding (which means potential of production downtime)
2. Increase suction pipe diameter to reduce suction piping flow velocity, V but maintain piping routing configuration. More reasonable option but need major piping work, which may cause more time
3. Install a small tank (100L) near the pump suction. But need to see if space constraint is an issue.
I am more inclined to Option #3. However, my question is, by putting in that small tank as intermediate tank, will that negate the actual suction pipe length from big 2000L tank to pump suction, and L is now considered to be length between 100L to pump suction instead?
In short, if original L = 25 metres, but by installing the intermediate tank, L= 2 metres? Thus reducing the acceleration head loss?
Need guidance. Thanks so much!
I am new here and need some guidance.
A new pump skid needs to be fabricated and fitted in a ready location at my gas platform. From what I heard, the old pump never worked - did not know a lot of details. Did a calculation to determine if NPSHa > NPSHr so there won't be repeat incidents. (suspect pump didn't work because of cavitation).
This pump skid is for well equalization purpose. Liquid service is diesel, from a 2000L tank, routed through a long piping to a pump (2 decks down), to be pumped to individual well to equalize the SCSSV.
I considered pressure of the tank (which is atmospheric), static head (fluid elevation from tank to pump suction), friction loss and acceleration head. from calculation, if taking into account the acceleration head, NPSHa will be < NPSHr, which mean that heavy cavitation occurs.
Acceleration head, Ha, formula I used:
Ha = LVNC/gk, where
L=actual suction pipe length (metres)
V=mean flow velocity in suction line (m/s)
N=pump speed (rpm)
C=pump constant factor. I used C=0.016
g=9.81 m/s2
k=liquid factor (a constant)
I want to explore ways to resolve the acceleration head loss issue, to ensure NPSHa > NPSHr. Options:
1. Reduce actual suction pipe length, L by reroute whole piping to make it shorter/more straightforward between pump suction and tank. But this will be a tremendous work, possibility of welding (which means potential of production downtime)
2. Increase suction pipe diameter to reduce suction piping flow velocity, V but maintain piping routing configuration. More reasonable option but need major piping work, which may cause more time
3. Install a small tank (100L) near the pump suction. But need to see if space constraint is an issue.
I am more inclined to Option #3. However, my question is, by putting in that small tank as intermediate tank, will that negate the actual suction pipe length from big 2000L tank to pump suction, and L is now considered to be length between 100L to pump suction instead?
In short, if original L = 25 metres, but by installing the intermediate tank, L= 2 metres? Thus reducing the acceleration head loss?
Need guidance. Thanks so much!