I am now calculating for pull-out bearing capacity of a headed stud.
From ACI-318 code appendix D, it is known that the ultimate bearing capacity = 8*Area of bearing contract*concrete strength
I am wondering how the 8 is coming, if we simply think of the failure mechanism - local crushing of...