  1. Cocorocox

    KKS (Siemens) to ANSI (General Electric) equipment description

    Im working on 850 Combined Cicle Power Plant, We have 3 gas turbine (siemens) x 1 steam turbine (GE). So I have a problem to connect KKS system from siemens to GE system, someone has an idea, how can i connect to put it in order? I want to keep a secuence!!
  2. Cocorocox

    GT's Air Coalescing Filters

    What is the essential work of this kjind of filters in turbines? In my plant(3x1 850MW), We have problems about humidity because of HR (>90% in Winter) so we are looking for the best solution; we are buying different brands to improve our air intake system. Is really "HR" a big problem? I'd...
  3. Cocorocox

    Gas Turbine Air Inlet Filtration dP - back-to-back filters.

    Probably , you have leaks near your measure point of pressure, when the air pass trough your filter and there are no hermeticity , you get a wrong measure. Check your instalation, if you have problems you should buy double packing for your filter. Good Luck