Dear All,
I have seen several installation Power Plant in Indonesia with Total Capacity of 100 MW, they make it 2 x 50 MW.
What is the reason of 2 x 50 MW installed, instead of 1 x 100 MW?
Thank you.
GeorgeTheCivilEngineer,
Yes, agreed. Superstructure loading data will make the foundations design more efficient.
But the point of my question is that, why Soil Investigation is needed to design the superstructure?
My understanding is that the design of superstructure has nothing to do with...
Dear All,
I am having confusion when my Senior Engineer in Company said that "Soil Investigation will impact Steel Structure for Boiler".
In my understanding, Steel Structure of Boiler will only be impacted by the load from the Boiler, wind, seismic, etc. And Soil Investigation will be used to...
Hi All,
In commissioning a Power Plant, if bypass capacity is 40% and we want to do 100% Load Rejection Test, is it recommended to go ahead with Load Rejection Test?
As if I am assuming, the excess load (60%) will go to safety valves? Is my understanding correct?
Kindly share your experience...
MintJulep,
I ask for suggestion, please do not ask me back [dazed]
TheTick,
Yes, you are right. I am so confused right now, Sir.
EnergyProfessional,
Actually, I have talked to the Dean of the university and after I shared the same story above (regarding my current job and my purpose to...
Dear All,
I would like to have suggestion to choose between Master in Mechatronics or Engineering Management based on your opinion.
I have a Mechanical Engineering background. I have been a Project Engineer around 3 years. Currently I am working in EPC Company with core business producing...
IFRs,
Based on what you said, "unless they are part of an assembly that requires stress relief". This means only for shell plate where nozzle attached (or etc.) requires thermal stress relief, right?
For example a tank consists of 20 plates with 30 mm thick for 1st course, 1 of the shell...
weldstan,
Alright, I understand why you said "Not if the PQR is impact tested." If the PQR of A 573 Gr. 70 plate is already impact tested, then it is certain that WPS of A 573 Gr. 70 can be used for A 36 plate.
But If the PQR of A 573 Gr. 70 is not impact tested and I want to use for A 36...
weldstan,
What do you mean by "Not if the PQR is impact tested."?
So, In my case stated above, the WPS for A 573 Gr. 70 plate can be used for A 36 plate, right?
Thanks JStephen,
So, tank with shell thick more than 25 mm is not required to be stress-relieved. The thermal stress relief is required for nozzles, flush-type cleanout fittings and flush-type shell connections.
IFRs,
And that is for nozzles, flush-type cleanout fittings and flush-type shell...
weldstan,
Alright, there are material specifications which include impact temperature requirement.
212197,
Thanks for the guidance!
So, if I have a WPS for A 573 Gr. 70 plate which is P-No.1 Gr. No.2, I can use it for A 36 plate (in which it is classified as P-No.1 Gr. No.1) or vice versa...