Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by kondori

  1. kondori

    Inadequate PWHT holding time for Carbon Steel piping in caustic service (NACE SP-0403)

    Thank you for your reply. The fluid design temperature is 50C. We have electrical tracing + insulation to keep the temperature at this level.
  2. kondori

    Inadequate PWHT holding time for Carbon Steel piping in caustic service (NACE SP-0403)

    Thank you, Andrew. Option No. 3 seems to be the most reasonable solution. I will propose options 2 & 3 to the project management (so they choose option No.3).
  3. kondori

    ASME QG-106.4

    We had four EPC contractors for our process plant project, and we did this. We made a database of all WPSs required and identified those WPSs which were common among EPC contractors. This way, we reduced the number of WPS/PQRs required. After approval, they were allowed to use any of those WPSs...
  4. kondori

    Inadequate PWHT holding time for Carbon Steel piping in caustic service (NACE SP-0403)

    Thank you all for your replies. For clarification, this is where we are at the moment: We are the owner of the plant (Quality Dep.) Caustic concentration and metal temperature show the welds to be in Area B of Figure 1 of NACE SP-0403. Additionally, our specification requires PWHT at 630C for...
  5. kondori

    Inadequate PWHT holding time for Carbon Steel piping in caustic service (NACE SP-0403)

    Thank you, EdStainless, for your reply. Update: Today, I found out that originally, they have been following the specification and performing PWHT acc. to NACE SP-0403. The reason why they have changed things and reduced the holding time & temperature has been due to excess distortion and...
  6. kondori

    Inadequate PWHT holding time for Carbon Steel piping in caustic service (NACE SP-0403)

    Our PWHT meets the requirements of ASME B31.3. That's not the issue. The issue is that we did not meet the NACE SP-0403 requirements.
  7. kondori

    Inadequate PWHT holding time for Carbon Steel piping in caustic service (NACE SP-0403)

    Dear all, We have a situation in our project (petrochemical plant construction) where in our caustic service piping (mostly 4-6mm wall thickness and small OD), all the weldments have been post-weld heat-treated, but it has been done acc. to ASME B31.3 (not as per NACE SP-0403 requirements). The...

Part and Inventory Search