The quality manager and I have been doing our own research on the whole subject matter but we don't have much welding experience. We've worked with a local lab for some of the testing, so we're contacting them to see if they offer any type of CWI services. Thanks all for your help.
The plan was for one of our lead engineers to sign off the paperwork or our quality manager. We're new to this which is why I'm on here for advise. So a CWI is required to sign off the the WPS, PQR and WPQ's?
Hello,
My company has recently started welding to ASME Section IX. I've attended some training on the matter but a lot still seems ambiguous. I've been told a CWI is required to witness all test coupons being welded. Is this correct? We no longer have a CWI on staff so I have some concerns if I...