Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. arawinda

    Highly varied concrete strength

    Dear MIStructE IRE, I personally observing process of cube making and curing. We follow standards without fail.
  2. arawinda

    Highly varied concrete strength

    Hi Friends, Recently I experienced a bit high variation of our strength results of C50 ready-mix concrete purchasing for slabs and columns casting. We expect 37.5 N/mm2 as 7 days strength for C50 (i.e. 75% of design strength as per Sri Lanka Standards). Can anybody help me on following...
  3. arawinda

    LP Copper tape in RC slab

    Thanks Ron, Any technical guidelines please....
  4. arawinda

    LP Copper tape in RC slab

    Hi, Is there any guidelines for installing copper tape (of lightening protection system) within reinforced concrete? I noticed that a copper tape runs in concrete slab just rest on the rebar net. Is it OK? Isn't there any risk of affecting inhabitants during lightening? Thanks.
  5. arawinda

    Alternatives for too much slab starter bars

    Hi friends I came again with a new issue at my project. As the photo shown, there are 10mm starter bars around all core walls which is difficult to handle as we cast the core wall 02 levels higher in advance than the working level for ease of supporting placing boom. Our procedure has to break...
  6. arawinda

    Too much conduits in slab

    @Tommy385: I have the same concern @MIStuctE: Yes. Done.
  7. arawinda

    Too much conduits in slab

    @Juan: 15mm layer out of 70mm compression zone is affected and it is unavoidable. Large number of conduits is the issue as it considerably reduce the amount of concrete in compression zone. According to ACI minimum spacing is 3 times the conduit diameter.
  8. arawinda

    Too much conduits in slab

    Thanks a lot @KootK. Really helpful.
  9. arawinda

    Too much conduits in slab

    Thanks @hokei66. My concern is not that. Is there a sufficient concrete amount to bear the design load?
  10. arawinda

    Too much conduits in slab

    Hi, Please see attached photo showing spreading electrical conduits over 140mm thick slab. Cover to steel is no issue but I doubt about amount of concrete actually in the slab as conduits consume considerable volume. I'm searching for limitations, if any, for amount of voids allocation withing a...
  11. arawinda

    Quality assurance in high rise building construction

    Hi, I am currently involving in construction of 50 storied building. Would you please to share some guidelines/specifications/documents regarding "quality assurance in high rise building construction"? I need to prepare a quality assurance plan for project that include what quality matters...
  12. arawinda

    Rapid hardening problem in secant piles

    Hey friends, Its me came with new problem. Due to a mistake of rig operator, a set of 4 casings was fallen back into borehole. Can you please suggest any suitable method to extract them out. Top of casing set is at around 7-8 meters below the ground level. This trouble is now becoming a...
  13. arawinda

    Rapid hardening problem in secant piles

    Ron, We are in the process of analyzing chemical in water and soil. Will come back soon once receipt of results. BTW, what is SLTA? [smile]
  14. arawinda

    Rapid hardening problem in secant piles

    But we tried with three different suppliers. at least one pile concreted from each supplier resulted in premature hardening.
  15. arawinda

    Rapid hardening problem in secant piles

    In our site, in which still secant pile construction in progress, we experienced concrete had been hardened rapidly (in less than initial setting time) in several piles along the boundary closer to sea. This pile line is about 120m from sea. Could you please state possible reasons for this and...
  16. arawinda

    Fire protection construction grout?

    Case in my site: Structural designer specified to keep 25mm cover to concrete walls and columns for fire protection and due to unrecoverable mistake we had to cut concrete layer in one side of column up to reinforcement bars to align particular column with others. Next, column should be...
  17. arawinda

    Cutting top net steel after concreting

    Image shows that partially cut concrete surface in a bath room for inserting gully box, which could not be placed during concreting. There is 10mm tor steel bar (hogging steel for slab over beam), which is @175mm C/C. Imagine gully box location cannot be moved and steel bar should have to been...
  18. arawinda

    Concrete compresive strength prediction

    Dear friends, usually we crush test cubes at 7, 14 and 28 days after casting and use attached figure to verify the compressive strength. But sometimes we missed exact date. May be we have to crush it on 10th or 29th day due to practical matters occurred at site. So I want to know if there is any...
  19. arawinda

    probelems in concrete surface finish

    Hey Hokie [colorface], See picture attached for rf details of particular column... It is at 3rd floor level of 28 stories building. Is it steel congested?? I think there is sufficient space for aggregate movement and...

Part and Inventory Search