  1. ASMEQC

    Retubing a warped heat exchanger bundle

    Have you tried rolling the vessel? Rolling might bring the supports close to alignment.
  2. ASMEQC

    process pipe qualification range

    Have a look at QW-403.1
  3. ASMEQC

    process pipe qualification range

    If the welder took a test using P45 to P45 then he is qualified to weld P45 to P1 per QW423.1. But to make the weld a WPS (weld procedure specification) and PQR (procedure qualification record) for P45 to P1 must be done. You have to have a WPS and a PQR for the 2 materials welded together...
  4. ASMEQC

    Radiography Test in PV Elite

    Where in UW-52 does it say that T-joints are a required spot?
  5. ASMEQC

    high pressure natural gas piping

    We have been asked to quote on a project that involves building some small well house units with 2 small ASME pressure vessels (SEPARATORS) in them. We have been asked to quote just the vessels and to quote building the whole units. They will connect to the piping that is already in place. I...
  6. ASMEQC

    high pressure natural gas piping

    The above ground units are part of a underground storage. Gas is stored underground until needed then pumped to a distribution site. I would say it is a fuel gas. Some of the questions i do not have answers to yet. Thank you all for your help.
  7. ASMEQC

    high pressure natural gas piping

    thanks for the reply's i will have a look in International Fuel Gas Code. this is above ground. the pipe sizes vary from small tubing to 4 inch. mostly A106-B. Pressure is around 1500psi to 2000psi. one of our customers will own the pipe units. No this not part of any power plants. I am...
  8. ASMEQC

    high pressure natural gas piping

    hello fellow members i am wondering if there is a building and welding code for high pressure natural gas piping? This will be in the state of Illinois.
  9. ASMEQC

    Min. preheat and inner pass temp for SA516-70 8" thick

    weldstan.... thats along the range i was thinking. These test plates are very expensive i just wanna make sure i am right. david339933.... Appendix R only has the recommendation of 175 degrees for plate over 1". Thank you all for the info
  10. ASMEQC

    Min. preheat and inner pass temp for SA516-70 8" thick

    First off thank y'all for the responses metenger... i must be missing something i have been looking in ASME VIII div.1 and XI and i have not found anything regarding preheat other than 50 degrees.
  11. ASMEQC

    Min. preheat and inner pass temp for SA516-70 8" thick

    Hello All, Where would be the best spots to research a recommended pre-heat and inner-pass temp for SA516-70 plate that is 8-1/4" thick. Thanks in advance for and reference.
  12. ASMEQC

    Pressure vessel nameplate using ASME as design code

    Sorry i am narrow minded i guess. I just assumed that we were talking the US not other country's. My bad.
  13. ASMEQC

    Pressure vessel nameplate using ASME as design code

    toohotforme Markings such as "ASME", "ASME Standard," or any other marking including "ASME" or the various Code Symbols shall not be used on any item that is not constructed in accordance with all of the applicable requirements of the Code. with the statement above that comes from the foreword...
  14. ASMEQC

    Pressure vessel nameplate using ASME as design code

    If the vessel tag is not stamped with the ASME certification mark. Your not supposed to use any reference to ASME. But i see ASME VIII Div. 1 stamped on lots of nameplates these days with out the vessel being code. I think if you look in the foreword of the code book it might explain it. Just...
  15. ASMEQC

    Welding 20ga Stainless Steel without distortion

    EdStainless We are back stepping the welds and skipping around to minimize heat input. racookpe1978 We are unable to use brazing at this time due to not having a procedure and to little time to make one. We have successfully completed the welding without distortion but only by switching to...
  16. ASMEQC

    How many copies of the BPVC does a cargo tank maker need?

    Sean999 We manufacture ASME vessels and we only buy one copy of each. Just make sure that everyone that may need info out of them has access to them. And yes they are very expensive.
  17. ASMEQC

    Whether Sight Glass Should be Assembled with Vessel while performing Hydrotest ??...... Answer : NO

    We always hydro with the glass installed. The glass should always be rated higher then 1.3 of the MAWP and temp. Although we have had a few people install the wrong glass and it didnt work to well. To me the glass should be sealed before shipping and how do you know that it is without doing...
  18. ASMEQC

    Welding 20ga Stainless Steel without distortion

    Just an update we have now removed the 20ga section and going with 10ga. This will help to minimize the distortion. Thank you all for your input. tbuelna: if i may ask what is a joggled hole? The nozzle shown is a pad flange that is welded to the inner shell with a cone welded to the pad for...
  19. ASMEQC

    Welding 20ga Stainless Steel without distortion

    The nozzles are thicker material. The picture shown is the lagging for the insulation. I have been trying to tell the client that you cant weld it without distortion but they have required it with none.
  20. ASMEQC

    Welding 20ga Stainless Steel without distortion

    Friends I am inquiring to see if anybody has some helpful ideas to weld the project that is in the picture without the distortion. We have been using GTAW for the welding but have been unsuccessful to do it without distorting the shell in between the nozzles. Thank you in advance...