Do you have some guideline which you had recommended separation? Maybe just advise me of step or flowchart then I will make decision by myself. Anyway, I have to find local law to define the distance also.
Hi, LCREP
Could you advise me the website of the engineering department...
Yes, it helps me. but it's still in procurement process fabrication conditions still unknow. Can I assume to select pipe end instead of pipe except end? Is it practical selection for using API 5L?
Thanks for your answer but I'm still not clear for your answer that note "a" is specified both Pipe except end and pipe end.
My understanding for your answer is Pipe except end means, pipe is not included 100mm extend end and pipe end means pipe that already included 100mm extended.
I just would...
What is the different between " Pipe except the end" and "Pipe End" in API 5L Table 10 Tolerances for diameter?https://files.engineering.com/getfile.aspx?folder=b3fc3f65-722d-4e60-9d2a-4776c47b9c15&file=Capture.JPG