Hello
When the execution specification sent by the client doesn't consider Additional information and options (4.1.1), what shall the manufacturer do?
Who is responsible for ensuring that the execution specification is complete?
Thanks
UW-35 and the interpretation forwarded by David confirm that Code accepts the undercut regardless of its length provided the depth is less than 1mm or 10%.
Since the purpose of the Code is safety, Comity should know that this defect is not harmful to the pv integrity before issuing the...