Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. P

    B31.4 Weld Inspection "Per Day" requirement

    Thank you all for the guidance. Never had the opportunity to see pipeline being welded up. Having multiple welders working together explains a lot. FYI these are not cross country. None more than a few miles. Can't say anymore than that.
  2. P

    B31.4 Weld Inspection "Per Day" requirement

    A lot of 36" - 48", 1" wall, API 5L-60. Looking at the link for thick wall welds, the detail shows 10 passes using vertical welds for a 1" thick wall. On a 36" diameter pipe that's 3.1416*36*10 = 1131 inches of weld. Even at 100"/hr, that's a full day's work. Which brings me back to the "per...
  3. P

    B31.4 Weld Inspection "Per Day" requirement

    Appreciate the quick response. Will re-check what the fabricator is estimating for these welds.
  4. P

    B31.4 Weld Inspection "Per Day" requirement

    Hello everyone, Wondered if anyone had any experience with this: B31.4 2016 Para. 434.8.5.3 states that above a hoop stress of 20% of yield, a minimum of 10% of girth welds "completed each day" are to be inspected. What does this mean for large pipes where one girth weld takes most or all of...
  5. P

    Nozzle rotation and flexibility for nozzle with internal piping

    Gentlemen, Appreciate your responses. I will re-incorporate the rotation as per your recommendations.
  6. P

    Nozzle rotation and flexibility for nozzle with internal piping

    Hello, I have an API-650 tank, with two 24" nozzles. One nozzle has internal piping going back to the center of the tank, the other has none. The internal piping would be supported about every 20' with goalpost type supports (no hold-downs). I am trying to determine what effect the internal...
  7. P

    Line List Info on Piping ISOs?

    For the PE who has to stamp the iso - having a note that says "See Line List" for the design conditions and hydrotest pressure is a bit like signing a blank check.
  8. P

    Pipe Risers Height

    I have always seen face of flange set at least 12" above top of grade. That's for process or cooling water lines. Drain lines probably aren't as critical.
  9. P

    Caesar Giving Displacements more than the allowed guide gap

    Probably a negative movement in the gravity case. Then a positive movement in the thermal case. The thermal movement will then be the absolute sum of the two, therefore greater than 3mm.
  10. P

    FEA on pipe flange below MDMT

    Thanks to you both for your input. We'll have to wait and see what the Client chooses to do.
  11. P

    FEA on pipe flange below MDMT

    We have some existing A105N, B16.5 flanges that have not been impact tested. New upset conditions would be -48C at nearly atmospheric pressure for 15-30 minutes. Most of the time it will be at ambient. We have done pipe stress analysis and checked flange leakage, both are fine based on...
  12. P

    vertical load check of bare piping on beams

    Here's one reason not to rest bare pipe on round bar. See attached below.http://files.engineering.com/getfile.aspx?folder=013bf15d-7bcb-42b4-9ed8-b0a060205a13&file=Round_Bar_Erosion.pdf

Part and Inventory Search