Im working on 850 Combined Cicle Power Plant, We have 3 gas turbine (siemens) x 1 steam turbine (GE). So I have a problem to connect KKS system from siemens to GE system, someone has an idea, how can i connect to put it in order?
I want to keep a secuence!!
What is the essential work of this kjind of filters in turbines?
In my plant(3x1 850MW), We have problems about humidity because of HR (>90% in Winter) so we are looking for the best solution; we are buying different brands to improve our air intake system.
Is really "HR" a big problem? I'd...
Probably , you have leaks near your measure point of pressure, when the air pass trough your filter and there are no hermeticity , you get a wrong measure.
Check your instalation, if you have problems you should buy double packing for your filter.
Good Luck