I forgot to tell you that we are working on the detail design of one EO/EG process plant. The current setting of the relief valves in P&IDs are as I described above.
CHD01-your comments give me very good instruction. Now,we are working on a process plant(EO/EG).The relief valves designed by basic design suppliers can not satisfy the requirement of " at least one inspection per year" of the Codes.Because all the relief valves in PIDs are single and...
I have read that article and I think the viewpoint in it is useful.We should enhance safety by learning the accident more effectively.We should not stop hazard identification and analysis during the mormal operation of plants.
Thanks