Hello again. There seems to be some confusion wit my first post so let me clarify some points.
When I level a pad, for example, I first clear the trees with the Cat. Then, I take shots at 25' intervals for the whole pad area. I then put these on the corners of a grid and average all the...
Thanks to both of you for the reply. I do have one more question though. It concerns the averaging of the corner values for each grid. I have seen one guy who SPLITS the corner values by CUT/FILL. Example: if the grid spacing is 25x25 (625) and one corner is cut and the other 3 are fill, he...
Hello:
Can anyone point me to information on the web about how to do cut and fill calculations for grading?
Say I have a 500' by 700' area. I take shots every 25' to form the grid. I would like to know the total cut/fill for the site (not worried about compaction -- yet)
I've checked mainly...