A transformer running at rated temperatures for their entire life may have a lifespan of only 10 years. Sizing slightly larger can dramatically increase lifespan.
One consideration is the lifetime cost of losses based on the anticipate generation profile. The ideal design for a generator that...
Rather than 5 phase, the 5F tower has a double bundle in the center and single conductors at the edges. Seems like basically two separate circuits with the middle phase mounted on the same insulator. Something like this:
A------B
---CC---
B------A
Larger diameter wires, more wires per phase, and tighter phase spacing all reduce impedance. Equilateral triangles will have lower impedance than flat arrangements.
I am used to thinking about a system than has 115/15 kV substation transformer that feeds several circuits that each have dozens of 15 kV/240 V service transformers. Energizing one of the 15 V circuits causes inrush to the 15 kV/240 V service transformers, which is in turn fed by the 115/15 kV...
Seconding crshears suggestion to ensure you design the tie with adequate isolation points to allow for maintenance of either bus without taking both busses out of service. Beyond that, the second tie breaker adds very little value.
Utilities often have transformer ratings that take into account the expected duty cycle of a project. A 12 hour duty cycle of 325 MW discharge for 4 hours followed by 200 MW of charging for 8 hours should allow for a somewhat smaller transformer as compared to a constant load.
Has the ISO...
Substation transformers are custom built, so there is a little bit more flexibility with the impedance of substation transformers as compared to distribution transformers. A friendly manufacturer's sales person could give you some guidance as to how much it would cost for a slightly higher...
On possible alternative is to ask them for calculated ratings under alternate operating conditions. For example, I have asked vendors to calculate nonstandard conditions such as:
an ambient adjusted rating for a zero degrees C ambient
a rating assuming the long time overloading parameters in...
As LittleInch pointed out, consider the refueling logistics when determining the appropriate size for the new tank. If your requirement is for 24 hours of actual run time, it may be helpful to size the the tank to allow for at least 6 months of routine testing loads in addition to the fuel to...
The typical inrush curves for transformers assume an infinite bus approximation. For an islanded system with a transformer larger than the generator, that will be a rather poor assumption.
I am rather confused that the links suggest that 0.5% probability means something will never occur. If...
Oil containment rules vary by state. The requirements in my region are that oil cannot escape into the watershed. For temporary installations far from water, the oil spill prevention plan would typically be to remediate any oil spillage by removing all contaminated soil. There is cost analysis...
The 230 kV/66 kV ratio is a bit higher than typical for autotransformers. That being said, it seems weird to have the 66 kV system ungrounded.
Many regions are eliminating tertiary windings on 400/230 kV autotransformers.
The GE publication The-whys-of-wyes provides good info on why to choose each configuration.
Your application also matters. Do you have a load, a generation site, or a mix of load and generation? Increased distributed generation is make wye-delta-wye transformers more attractive.