Hi,
First post ...
Using MS Project 2016
When I enter single day tasks (forecasted) they split across 2 days. On further investigation, it's because MSP changes the start time for these tasks to irregular times, such as 11:12 AM, then the 1 day task spans across 2-days.
Weird thing is...