I am using MS Project 2010 to create a construction schedule based on a 9 days on, 5 days off shift. How do I change the working time to reflect this? I can do it manually but don't want to input two excepetions for each month of the project. Is there an easier way?
Hi,
I am putting together a construction schedule based on a unique working time of 9days on, 5 days off. MS Project 2010 does not seem to allow me to overlap exceptions from week to week. I can manually input this working time for each week of the month but I am searching for other ways of...