  1. LuisCuellar00

    How to calculate pressure increase in a closed liquid filled cylinder?

    thread391-15161 Hello guys; So 2015 I had the same question that in the above post, and found usefull information in an API standard about hidraulic expansion and pressure increase that can complement. You can refeer to API STANDARD 521 SIXTH EDITION, JANUARY 2014 Pressure-relieving and...
  2. LuisCuellar00

    Flow measurement of Corrosive liquid with sticky solids

    Hello again. EmmanuelTop: Our hexane has up to 0.01% of Water, do u think an adsorvent can dry it lower? any water in remaining in hexane will react. Do you know anny supplier or literature that I can Check? georgeverghese: I have contacted the supplier, I let you know what they think. And I...
  3. LuisCuellar00

    Flow measurement of Corrosive liquid with sticky solids

    Hi. We have been struggled with a hard application in flow measurement: S2Cl2/Hexane = very corrosive, its flammable, Solvent, and has little solids that sticks ( Lets say 1 Kg per TON) We need to dose from Tank to Reactor Tank = Glass lined 1,000 Gal with agitation Reactor = Glass lined...
  4. LuisCuellar00

    Mean time To fail in Pressure Gauges?

    Mikehalloran Somthing like this. http://www.wika.us/23x_34_en_us.WIKA.
  5. LuisCuellar00

    Mean time To fail in Pressure Gauges?

    Thank you for all your responses, there are some grat Ideas. In your experience how much time could a manometer be in operation with out failing, if installed in a correct application. Dawn2: I read al wika information it will be put in good use. Thx.
  6. LuisCuellar00

    Mean time To fail in Pressure Gauges?

    Hello fellow colleagues. Since a 4 years of growth, construction & startup of a new production lines in our fine chemical facility the engineering department will be focusing in improvement projects. I detected increasingly failures in pressure gauges. After some investigation we found out we...
  7. LuisCuellar00

    Microsoft Project %complete and status date

    Try using "Update Project" option, located in Project tab. Is that what you looking for?