  1. pocketgui

    how to fix start date, end date, work, and let the units float?

    Hello. I have the following question: How can I fix the start date, end date, and work for a task, and let the units adjust to meet the criteria? I want to link these tasks to project start and project finish. Alternatively, how can I fix the start date, end date, units, and let the work...