I am now working for small capacity industrial boiler. The capacity is around 90TPH superheated steam. This is a trial project to us and I am trying to figure out what basic design calculation am I going to use. I am looking for a better formula in computing the performance calculation.
82264
I would like to know what things to consider before we can do alteration works to a Blowdown tank. The blowdonwn tank is ASME coded and the alteration that is going to do is to add additional 1 piece of nozzle.
Thanks
82264
We have a case that we will use existing blowdown tank which was not actually used, this unit already passed the ASME Code Section VIII means to say all requirements were completed. We have now a new project which needs a blowdown tank, the design condition of this new project is slightly higher...
I am working in a steam drum which is basically under ASME code Section I, we are using a program in Japan wherein the formula used in calculating the drum head is in ASME code section VIII, they been using this long time already even in ASME Stamp required project. But here in our country, we...
I am working in a steam drum which is basically under ASME code Section I, we are using a program in Japan wherein the formula used in calculating the drum head is in ASME code section VIII, they been using this long time already even in ASME Stamp required project. But here in our country, we...
In the strength calculation of DRUM HEAD, which is best to use in computing the tsr or required thickness of drum head, is it in the ASME Code section I? or in ASME Code Section 8? If ever I choose section 8, what will be the chances that I can pass during ASME renewal? Please anyone can advice...