Thanks folks-
So cvg- what's the formula there? Is it the obvious-which would be unit height over vertical rise? So setback on a 1H:2V would be 5/2 or 2 1/2"? Spreadsheet is the way to go, I agree. And I should be frank-I am the distributor, but the unit height CAN vary, so the manufacturer...
Ok that's a definite option! I guess I can go to an engineer supply and grab a scale- as you call it- is my lack of experience showing yet? If I did want to apply a formula, do you have any idea how I could do it? I'd like to be able to do it for all batters, from 1:1 up to at least 1H:10V...
Hello Folks-
I'm in need of some math help. I would love to be able to give a rough idea of how much setback in inches is required per course of segmental retaining blocks to achieve a certain batter. For example, if I want to build a wall at an 8:1 batter how much setback in inches per...