  1. abspark

    Fault level limiting in 11kV distribution

    Site growth took our fault level beyond the existing equipment's 250MVA rating with a predicted level of 350MVA. Our short term solution involved two tapped reactors (operating in parallel) to segregate the older 250MVA network from the new 350MVA rated equipment. As more site load is added and...