Froude,
I fully agree, we have multiple areas of storage (basins, parks etc) which are not utilized in storms smaller than 2-5 years.
I can also see how small storm events would be very sensitive to modelling assumptions and the readings could also be distorted by blockagaes etc. After doing...
We are in Autum moving into winter so the chances of a significant storm event are low(Sub Tropics).
My question is even if we were to put flow gauges in etc and measure a 1 year ARI storm event (hopefully higher), would this add any addtional value in the model ? and do people commonly do this...
Hi all,
A brief introduction, I am a civil engineer currently managing a multiple phase design project. The second and third phase of the project is basically a civil design project of roads and a upgrade of an existing drainage network (Urban). However the first phase of the project is...