    MS Project task duration vs work calculation

    Good point- The file I am working with was originally established as an effort drive file-- That created a problem for me in that it altered the duration of my schedule based on resource loading-- I then turned ED off, but am still having some problems. I will start over with a scratch file
  2. FLCIVILENG

    MS Project task duration vs work calculation

    I am trying to setup a design schedule in MS Project-- The issues i've run into is that after I establish the precedence diagram/schedule and assign time to each activity(in days), and then resources to each activity, that MS project applies the resource cost(hourly rate) to the entire activity...