In ASME B31.3
341.4.1
It states that:
"...at least 5% of fabrication. For welds, each welder’s
and welding operator’s work shall be represented."
For example, 1 welder have made 10 joints of for piping with the same size. Does this mean only half of the weld should be examined? Or it...