Thx to all.
I have done on Hydrostatic test at 33bar and also set safety valve at 22bar. Now, i'm just waiting to do steam test before start wet run for my new mill tomorrow.
Regards
I just want to know its steps before we do safety valve setting.
My boiler information:
Design Code: BS1113-1998
Max. Permissible W.P: 2.414 N/mm2
H.T Pressure: 3.621 N/mm2
Max. Continuous Rating: 20,000kg/hr
Hi,
I'm a newcomers in this field.I would like to know if somebody can tell me on how to set the safety valve for the new boiler,20MT. My new mill will start on steam test tomorrow and also to set the safety valve.If someone can tell me,it will be much appreciated.Thanks.