  1. Ali Hayat

    Steam Drum - Separators Replacement

    Is there any code which supports that butt weld covers socket welds
  2. Ali Hayat

    Steam Drum - Separators Replacement

    This is not a boiler steam drum that is why we are using Section VIII Thank you for mentioning PWHT exemption code There is another question regarding WPS IS there any separate WPS required for socket welds, we have already butt weld wps
  3. Ali Hayat

    Steam Drum - Separators Replacement

    Thank you for your replies @metengr & @christine74 Regarding PWHT, we are following ASME VIII Div 1 UCS-56 which states that PWHT is applicable for P1 material unless preheat of 200F is applied for 32mm to 38mm thick shell plates
  4. Ali Hayat

    Steam Drum - Separators Replacement

    Thank you sir for answering all Can you please help me with the following as well I have WPS for P.No 1 Group 1 SA 106 Gr. B, Will it be approved / applicable for SA 516 Gr 70 P. No. 1 Group 2?
  5. Ali Hayat

    Steam Drum - Separators Replacement

    Thank you for your reply. Can you please help me with the following as well ? Our company does not contains R stamp, now this project is under manufacturing stage of separators that will be installed in May 2017. What will be the process for R stamp? and what inspection & testing processes...
  6. Ali Hayat

    Steam Drum - Separators Replacement

    Question: We need to replace existing separators from a steam drum with new separators. Can Separators be supports welded with shell ? Is it a violation or it will require R stamp ?