There is no better way of estimating than verifying all the parameters one by one if you are bothered of having your Bid over and or under bid. If it is rush, working overtime on it will make a difference anyway its just for say: a week.
For me its not practical to compare the cost of MEP...
I totally agree with jraef, the new cables might be damaged during the pulling in.
How about this one:
If the capacity of the existing cables are sufficient for the new MCC, try to test the insulation resistance level of that cables, if its still intact why bother to change it?
Hello Guys,
I'm new here and I don't know yet if there are threads related to my question.
We ordered this Medium Voltage Switchgear (15kV) from Italy and we make sure that during the ordering process we specified a 60Hz System since we are here in the Philippines; Yesterday we found out that...