    Mud Sill placed off-center on Footing

    I have been working on building a 20x30 house on a frost-protected slab. The plan for the slab was to be a thickened edge, monolithic, Alaskan slab, 2 feet tall with 16" wide footings and two 1/2-inch rebar top and bottom and a 1 foot wide by 8 inch deep grade beam down the middle of the 30...
  2. buildhome

    Groundwater close to bottom of foundation excavation

    Thanks for the replies. I dug my foundation drain down at least 6 inches below the level of the trench I had. So, I have a trench in a trench: a 5 foot wide trench with a 1-1/2 foot wide by 6+" deep trench around its outer perimeter. This was easier than the curtain drain and should serve to...
  3. buildhome

    Groundwater close to bottom of foundation excavation

    Thanks for the reply, pba. The geo I have been talking to offers plenty of advice but says there is not much a site visit will do to provide more information. Though the water level has dropped to 4-5 inches below the bottom of the trench the soil is staying wet and non-compactable. The...
  4. buildhome

    Groundwater close to bottom of foundation excavation

    A quick update, though opinions are still welcomed: I've decided to dig the curtain drain, trying to get it at least 1 to 1-1/2 feet below the trench bottom. Reading I have done on such drains brings up different opinions as to type of backfill, 1-1/2 inch stone wrapped in fabric vs. sand...
  5. buildhome

    Groundwater close to bottom of foundation excavation

    I am owner-building a 30x20 story and a half home in NE Vermont on a frost protected monolithic (thickened edge slab. The site has approx. 5-6% slope, silty soils and is at the bottom of a watershed of approx. 250 acres that goes a mile back. Excavation was done to get the topsoil off at the...