  1. JoeJersey

    Visual inspection requirements for ASME B31.1

    Thank all of you for your input, we initially interpreted the code to view all stages of the welding process. We now see that you only have to VT the final weld.
  2. JoeJersey

    ASME B31.1 VT requirements

    Stanweld - Thank you for your help so far. Just so this is clear; B31.1 - VT is not performed on the welding operation but on all welds in the system after they are completed B31.3 - VT is up to the inspector, for example if the inspector witnesses the fit up through Cap weld of a handful of...
  3. JoeJersey

    ASME B31.1 VT requirements

    Additionally, does the VT requirement mean inspect the fit up of pipe, root weld and all fill passes after?
  4. JoeJersey

    ASME B31.1 VT requirements

    Stanweld, We decided to use B31.1 for heating and cooling because our company will operate the plants for long periods of time and they wanted to choose a code that would insure proper welding so there are no problems down the road. One Plant we built had 42" pipe headers and distribution for...
  5. JoeJersey

    ASME B31.1 VT requirements

    I originally posted this in another section before I saw this code section. We (as Owners/operators of Combined heating and cooling plants) are trying to identify the "necessary" visual requirements for ASME B31.1 on a Chilled water, condenser water and hot water systems. We interpret the...
  6. JoeJersey

    Visual inspection requirements for ASME B31.1

    Metengr, So its 100% VT of all welds in the system? Do you know if we were to RT or UT 5% of the welds does this eliminate the 100% VT? 136.4.2 states as necessary, and then later on states all welds. We had an inspector for both on site and offsite fabrication any time they were welding...
  7. JoeJersey

    Visual inspection requirements for ASME B31.1

    We (as Owners/operators of Combined heating and cooling plants) are trying to identify the "necessary" visual requirements for ASME B31.1 on a Chilled water, condenser water and hot water systems. We interpret the Code to require 100% Visual on all welds period (Table 136.4 in 2001 version of...