when u specify 730d from for example 2008/Feb 22, MSP will put the end date in 2010/Dec 09, because it is assuming that u don't work at weekends, so you lose 2 days per week.
If you specify 24mon, the end date (in my case) is 2009/Dec 24, because in the Tools->Options->Calendar my MSP defines 1...
Hi!
I'm managing a lot of small projects on a small team, sometimes having the need to have a global view of my team allocation.
I thought MSP could help me on the task of controlling overallocation, but I met a couple of unexpected problems...
For me, the most serious is the following:
I have...