  1. HerveBaron

    The 2 drivers of an Oil & Gas Project duration

    Project Critical Path (CP) law “The time it takes to build an Oil & Gas facility is the time it takes to build its pipework. Pipework construction effectively starts once engineering is nearly completed. Engineering effectively starts 2 months after half the equipment have been ordered.”...