    Sight Glass (EX area)

    Hi Is it possible to used Sight glass in ATEX area (Zone 1 group 2)? Glass is sometimes not recommended in EX area. A low conudctivity fluid (lubricating oil) will flow through the sight glass. This oil may be charger by a fine filtration upstream filter. I would like to avoid potential static...
  2. Matchess

    API 614 Why Metal mesh or stainless metal filter elements are not acceptable ?

    Hi Someone know why according to API 614 part 2 and 3 metal mesh is not acceptable for oil filtration ? 1.6.4.4 Metal mesh or stainless metal filter elements are not acceptable Regards
  3. Matchess

    Rundown tank restriction orifice in lube oil system of rotating equipment

    Hi Be careful, it is easy to overfill a run down tank as is is really difficult to size the rundown tank overflow line. In this line you have gravity flow (the line is probably not 100% filled with oil, so you have a mix between air and gas. This flow will be probably not stable if the oil...
  4. Matchess

    Centrifugal compressor in stone wall region

    The stone wall exact location in Compressor map is often unknow by Compressor manufacturers. Running on this location will generate low frequency vibration which may trip or potentialy damage your Compressor. These conditions are generally considered less critical then surge conditions.
  5. Matchess

    DGS acceptable reverse pressure

    Hi I currently design an expander with a tandem dry gas seal. On the primary vent line (connected to flare)a Pressure control valve set at 3 barg is installed. This valve allowed to have always a minimum differential pressure across segondary DGS (required by DGS manufacturer). However, before...
  6. Matchess

    API 686 Max number 5 shim requirement

    Hi Someone know the technical reason about the maximum 5 shims requirement number under machine foot (potential untightening screw problem ?)specified in API686). same question about the maximum shim thickness of 12 mm ? Regards
  7. Matchess

    ASME B16.5 minimum nuts thickness

    Yes it is standarde ASME B16.5 fLanges with the valve face to face dimension in line with B16.10
  8. Matchess

    ASME B16.5 minimum nuts thickness

    I will use ASTM A194 B8M material (stainless steel 316) The stud and bolt will have ISO threat. The pipe will be in cryogenic conditions and will never reach realy high temp (max 100 °C). Sometime with flange valve it is not possible to install Heavy hex, but only Hex (not enough space between...
  9. Matchess

    ASME B16.5 minimum nuts thickness

    Hi AMSE B16.5 recommend to use heavy hex. However it is only a reommmendation, is it possible to use hex (smaller nuts) and why ? What is the minimum nuts characterisics or size ?
  10. Matchess

    Dry gas seal, separation gas loss

    In this configuration, the expander proces gas is natural gas @ 30 barg. The vents are piped to safe area and I'm not really concert about corrosion (tank 100% in stainless steel). My concern was more about potential DGS contamination by oil mist. Do you think that this is a real risk ? I can...
  11. Matchess

    Dry gas seal, separation gas loss

    Thanks for your feedback. The machine is a exapnder - generator, the expander (on high pressure part) drive the generator (low pressure part) The gearbox (low presure part) reduce the spped between high and low speed shafts. The high speed shaft is equiped tandem dry gas seal(with intermediate...
  12. Matchess

    Storage of turbomachinery spare rotors

    hi there is recommendations on API 686.
  13. Matchess

    Dry gas seal, separation gas loss

    Hi I have Turbo generator with tandem dry gas seal and carbon ring on gearbox side. I would like to know, how long the machine can remain running in case of separation gas loss ? My concern is about DGS potential contamination by oil mist. In order to avoid oil migration (on DGS) is it...
  14. Matchess

    API 614 part 4 applicable for labyrinth and carbon ring sealing ?

    Hi Someone know if API 614 part 4 is applicable for labyrinth and carbon ring sealing or if it is only applicable for Dry gas seal ? Especially the requirements for seal gas and filter sizing. Regards Matchess
  15. Matchess

    Gas leak test, pressurized oil system

    Hi all, I design a pressuriez oil system for an expander-compressors (acc. to API614 firth edition annex G & API617 Part4) The operating pressure of the oil tank is > 60 barg with flammable gas. The design pressure of the seal gas oil system and compressor/expander/bearing casing is > 90 barg...
  16. Matchess

    Expander-compressors pressurized oil system, Gas leak test required ?

    Hi all, I design a pressuriez oil system for an expander-compressors (acc. to API614 firth edition annex G & API617 Part4) The operating pressure of the oil tank is > 60 barg with flammable gas. The design pressure of the seal gas oil system and compressor/expander/bearing casing is > 90 barg...
  17. Matchess

    Location PSV upstream or downtream a check valve blocked in closed position ?

    Good morning I am designing a lube oil system for a turbo expander This turbo expander is supplied with two oil pumps (1 for normal operation + 1 for back up) A check valve is placed dicharge line of each pump and I am asking if two PSV placed upstream of eash check valve are required to...
  18. Matchess

    Mawimum tolerated build up back pressure for a Rupture Disk

    Thank you for your quick and interesting responses Latexman, I am not quite sure, I correctly understood your answer. In my case: The PSV and Rupture disk set pressure are the same (equal to 25 Barg) So, If I follow the guideline from your former company. The alarm set pressure will be 25...