Can you elaborate on "three enclosure walls"?
I will be asking the geo consultant for more information. But now I still have some general questions.
1. Because the structure is at the middle of the slope (the blue line will continuous down at around 20 degree, so the lowest point...
Thank you.
It is a two storey industrial structural. Looking at the geo report, there are around 1-2m fill and then clay underneath.
I am going to use drilled rc piles (not footings as SlideRuleEra mentioned) and rely on its bearing and skin friction to resist gravity loads. In this case how...
As shown below, I have this structure on a slope site (up to 6m height at the front). The cyan ones are the piers as columns to support concrete slab (shown as red) above.
My question is what is the effective length of piers/columns (6m or more than 6m to consider the restraints from soil)? I...