thanks mate , I work as Engineering Manager in a MEP contracting company and the Client aware of this Design Error but he asked us to proceed to avoid the project delay then now he used the specification clause to reject the claim .
MEP Contractor Noticed a serious Design Error in Pump Head which it is almost 150% of the Design pump Head ; Consultant agreed the contractor calculations and revised selection . Contractor raised a claim for the additional Cost to avoid the design Error but the Client cost Engineer referred to...
I have a situation where the sprinkler pipes are 9 meter away from Steel beams ;consultant advised to install the sprinkler main piping attached to the beam and sprinklers drops will be 9 meters . our proposal to provide low level secondary steel structure to enable us to support the fire piping...