    1959 Steel Deck Identification

    Thanks a lot Jae for the references, appreciate your input!
  2. generick

    1959 Steel Deck Identification

    Hey all, Looking at some old structural drawings and noticed a steel deck called out as what the pic shows. I'm assuming the 18 signifies the gauge of the deck and the depth of the deck being 2" but I'd like to see if other engineers have come across this specific designation. Thanks!
  3. generick

    Residential Strip Footing Questions

    Apologies if I left that info out from my initial question. This is a residential structure with an existing 2x8 stud wall that goes up 21 feet tall. 2-story house but this wall in particular has no intermediate floors due to a high-ceiling layout. The multi-slide configuration should weigh...
  4. generick

    Residential Strip Footing Questions

    Thanks for all your input!
  5. generick

    Residential Strip Footing Questions

    Hey all, I got a project where owner wants to incorporate sliding doors with a pocket wall. I'm having some doubts in assessing the existing foundation in Enercalc wherein: 1) For assessing existing strip foundations, would the axial loads from the trimmers/jacks to represent a localized point...
  6. generick

    Ship ladder to stair landing typical connection

    I suppose the top will be more of a slip-critical connection probably via angles and bolts. I am just having a brain-fart thinking of the connection as I have steel grating above the support beam that spans from column to column. I did a quick rough sketch below.
  7. generick

    Ship ladder to stair landing typical connection

    Hello, These are the only pics I've received from a client who is looking to build an industrial stair similar to this. Judging by the poor quality pic of the ship ladder consisting of C-channels for stringers - how are these normally connected at the landing? It appears to be "floating" and I...
  8. generick

    Assessment of Joist Girder Connection to Concrete Column

    @Brad805 Thanks for the clarification as well as adding the connection results for one side of the column. I am convinced to just proceed with designing a concrete corbel now. Also, unfamiliar with the program output but does T-V signify Tension-Shear?
  9. generick

    Assessment of Joist Girder Connection to Concrete Column

    @le99 I attached a snippet of the ETABS model that I have with the joist bearing on the girder while the girder bears on the columns. I believe I may have confused you into thinking that the joist goes directly to the columns.
  10. generick

    Assessment of Joist Girder Connection to Concrete Column

    @Brad805 The columns are 24"x24". To break it down further, the unfactored DL is 38 k and floor LL is 63 k. Can you express why the detail won't work for this loading? I was looking at concrete corbel but wanted to assess if this connection could handle it. @driftLimiter Thanks! I'll check that...
  11. generick

    Assessment of Joist Girder Connection to Concrete Column

    Hello all, How would you all approach this problem in terms of assessing whether this connection can support factored girder load of a 145 kips? See sketch and my understanding of the load path. If there is also a textbook reference or similar calculation done, that would be even more helpful...
  12. generick

    Concrete Framing System For Finance/Business Building With Irregular Layout

    @eng-erik It's pretty preliminary, we're talking about a conceptual plan moreso of a 10% design as of right now. @BAretired Yes I agree, fortunately the 2nd and 3rd floor are pretty similar, however, the 1st floor differs too much. It's all trial and error now in terms of placing columns...
  13. generick

    Concrete Framing System For Finance/Business Building With Irregular Layout

    Hello All, I've been tasked by my supervisor to come up with a preliminary framing plan for a 55 foot tall, 3-story building that will be used as a finance center. The preference of the building is to be entirely cast in place concrete and we are in a high seismic zone. I am in a stump trying...
  14. generick

    Question regarding car dealership canopy

    @canwesteng - not sure if I follow, however, your sketch looks a lot similar to the sketch of sticksandtriangles. Is this similar to what you were trying to convey? I'd like to keep the OWSJ system intact as the parapet wall at the roof level gets supported off the concrete deck. I have been...
  15. generick

    Question regarding car dealership canopy

    @human909 - I agree, torsion was already a big player when I first saw this canopy. I think we may have to compromise with the addition of the columns at the bottom left just as you said. I was just trying to make it work before looking into the addition of the column. @dik - No snow that...
  16. generick

    Question regarding car dealership canopy

    Hello, Thanks for the inputs so far. @MIStructE_IRE - I have designed my main columns with the addition of the moments from the cantilever. In terms of torsion of the primary (if you're referring to the main steel beam that runs E-W in plans), I haven't done much work yet into this, however...
  17. generick

    Question regarding car dealership canopy

    Hello all, The architects want to achieve this canopy look as you see below as well as a section cut and I am trying to come up with a way to frame this out. I have also attached my extruded ETABS model for more clarity of my intent. Essentially, I was looking to tie the cantilevered frames...
  18. generick

    Moment comparison of modeling wall on top of beams

    Hello all, I am using ETABS concrete frame design to give me the moments and shear values needed to design my beam. In this case, there is a wall on top of the beam and I have compared the moments for the following: Case 1: No modifiers Pos moment ~ 20.2 k-ft Neg moment ~ -35.4 k-ft Case...
  19. generick

    Modelling results of walls on top of beams

    Hello all, I am using ETABS concrete frame design to give me the moments and shear values needed to design my beam. In this case, there is a wall on top of the beam and I have compared the moments for the following: Case 1: No modifiers Pos moment ~ 20.2 k-ft Neg moment ~ -35.4 k-ft Case...