Hi all,
Just trying to detail some rebar in a slab that has a non 90deg corner.
Does anyone know what I should be doing in this instance thanks?
It's either do something really awkward or just keep it a mesh with the end bars a bit awkward.
Thanks in advance
Yeah its one of those, if we leave it leaning are people in the future going to be concerned because it looks like its overturning. I don't want that for the project and it is early enough to detail out.
Hi all,
I am currently detailing a precast box culvert, I know I could do it as a bottomless culvert with insitu slabs but would prefer to keep the full box unit to avoid scour issues. The proposed gradient to suit catchment study is 1 in 12 which means the end units lean about 5deg. I know...