I'm in the process of creating a schedule baseline. I would like to use "rolling wave planning" (Progressive Elaboration) to create my schedule - only put in detailed activities for near future work and high level information for the activities in the far future.
I'm wondering how this works...
I'm in the process of creating a schedule baseline. I would like to use "rolling wave planning" to create my schedule - only put in detailed activities for near future work and high level information for the activities in the far future.
I'm wondering how this works with creating a baseline...
I would like to import an external schedule into a master schedule I have but, they have different calendar options.
The master schedule has its calendar options set to 7 hr/day, 35 hr/wk. The external schedule has its option set to 8 hr/day, 40 hr/wk. This obviously affects how project is...