Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  • Users: gravitate
  • Content: Threads
  • Order by date
  1. gravitate

    New Task given - slightly outside my experience level

    Hello I am usually a mech installation engineer. I have Done large duct work installation and also helped do calculations before about the support calculations from steel work before. I am primarily a site guy anyway. But I am now in an office and have been given the task to do a preliminary...
  2. gravitate

    Happy new YEAR. Slight question about piping again please

    If we have a system with stainless austenitic pipe work and it is catagory M asme B31,3. It will be low pressure like 2 bar. 3- 4 inch stainless. Must it have a welded connection or is it acceptable for others like grey lock etc? I dont have my copy of ASME to refer to I am afraid.
  3. gravitate

    Pipe & Mechanical contract

    Hello I have been asked select companies to bid fore the mechanical and piping contract of a big nuclear project. This is a bit higher than my current level as I only know a bit about installation etc From a company what prerequisites would there have to be and how best to select the...
  4. gravitate

    Asme 32.1

    I have a question please. When installing stainless not category M pipe work that is Asme B31.3 is there anything in the standard about the flushing of pipe work? We have an engineer who thinks that all valves etc muct be removed and then the flushing of the pipe work takes place then you...
  5. gravitate

    pre-formed pipe and annealing

    When pipes are pre-formed, is it necessary to anneal the sections before they are mounted in a vacuum system?
  6. gravitate

    Pipe installation man hours issues.

    I have posted 2 attachements below. One from estimators piping man hours manual 5th addition and another from a contractor who priced some work for us. The contactor got a value for a straight pipe run handling and erecting of 0.72 man hours per meter for a DN200 pipe. They also claim this came...
  7. gravitate

    Construction work package

    What should be in a construction work package to be given to a site engineer? Specifically around pipe work with equipment on a nuclear site. Risk Assesment Method Statement Sign on sheet for achnoledgement of RA and MS Isometrics P & ID Pipe support Design Point of work risk assesment to be...
  8. gravitate

    Head Scratching I think I have lost it

    The top sketch is of 3 pumps which is in the P & ID. The bottom is what is in the actual design. As far as I can see there is no difference and no advantage dissadvantage of either. Am I wrong?
  9. gravitate

    Isometric

    This is from Caesar 2 but what is the thing that looks like some kind of expansion bellows? It is a stainless steel cooling water pipe.
  10. gravitate

    What does this mean please

    It is from a P and ID and cant find what it is anywhere. Thanks in advance.
  11. gravitate

    Installing pipework in concrete building.

    We have a concrete room with concrete walls, floor and ceiling around 7m high. Also there is pipework 8 inch to 56inch that is installed close to the ceiling which is then supported from the floor. How can you install this? The 8 inch is not a problem as it is stainless and can be manhandled but...
  12. gravitate

    Nuclear industry pneumatic pipework

    Is there any pros or cons from using compression fitting or screw in fittings for small bore stainless steel pneumatic pipework that supply valve actuators? Is there anything in the nuclear industry that is related to this at all please? Also it is possible to use seamless nylon tubing. I can...
  13. gravitate

    Buried pipe lines asme b31.3

    I do not have a copy of ASME B31.3 does anyone know if it is worth getting hold of one as we are trying to determine the requirements of buried pipework when it goes under roads and if it should be in sleaves? Also we are trying to find out the minimum depth it should be.
  14. gravitate

    Plant installation

    If the client is doing the design of the plant and equipment who should state where the field welds will be done and any modifications of the equipt for installation? The Client or installation contractor?
  15. gravitate

    What is this please?

    Could anyone tell me what this arrangement is? 2 pumps? The person I was going to ask is away for 2 days. A pump at the top and 2 vertical pumps lower down? I am pretty stuck. Thanks.
  16. gravitate

    small tank installation

    Hi basically we have 3 tanks to be installed in a concrete room of height 4.25 M. The tanks are 4.0 M high. We can not lift off the ceiling over the tank . How can we install it please any ideas? The tank is 2.5 tonnes in weight. As we can not lift from above is it possible to put embedded...
  17. gravitate

    Install pipe in vertical shaft

    We have 2 stainless DN 600 pipes to go side by side in a 750 x 3500 shaft. Is this space too small to install the pipe in sections welding every 6m or would it be preferable to get the pipe delivered while the building is in construction and lift the pipes in 1 length then weld at the top and...
  18. gravitate

    Construction of pipework

    We have a section of pipework which is 9 tons in weight. it has to be lifted into position along with 4 2 ton tanks. The pipe is 300DN. We have to put in 2 runway beams for the purpose of construction. Would it be cheaper to chop the section of pipework up int 4 pieces and lift them up with...
  19. gravitate

    Rework of piping systems estimation

    Dowes anyone happen to know if the figures quoted in 'Estimator’s Piping Man Hour Manual'by John S Page for welding, fitting, erecting etc include the amount of time for any reworks of pipe systems? If it doesnt then how do you calculate the amount for this? Such as weld failures, non level...
  20. gravitate

    Pipework quotation

    We have had a company do us a quotation for approximately 3km of buried pipework. In their quotation they have stated that for every 12m length of pipe they deliver they will presume 5 cuts on the pipe and 6 welds. Is this some kind of engineering industry normal? What I have done is presume...

Part and Inventory Search