I frequently have issues with MS Project 2010 adding phantom time into my tasks, as shown in my attached photo.
My task calendar is 24 hours (no holidays or time off), task type is Fixed Work, task constraint is As Soon As Possible, and the affected tasks match up nicely on the calendar with the...
Hi! I'm pretty familiar with MS Project's basic features (not so much with Actual Work, etc) and I am having trouble getting my tasks to obey their contraints.
The biggest problem is getting tasks with "As Soon As Possible" constraints to do a true finish-to-start.
-They have dependency links...