When you plot the three different water-cementitious material ratio, will the sand content change as well?
All three mixes they are plotting have the same #57 stone but
Mix 1 has low cement low water high sand
Mix 2 is middle of the road
Mix 3 has high cement high water and low sand
Should all...
Hi all,
I've been tasked with determining the load capacity of a "mezzanine" to meet OSHA requirements.
IBC 505.1 General. A mezzanine or mezzanines in compliance with Section 505 shall be considered a portion of the story below. Such mezzanines shall not contribute to either the building...
Hi all,
I'm brand new to this site and all forums for that matter.
I'm designing a rectangular storage unit that is basically a control station. The building is a box 10' wide x 30' long x 11'-6" tall.
My main question for now is designing the roof. The roof is made of G90 galvanized 11 gauge...