Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SDETERS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  • Users: pbc825
  • Content: Threads
  • Order by date
  1. pbc825

    Frp partial material resistance factor in Canada

    Hi, I’m hoping someone is able to point me in the direction of the partial material resistance factor to use for FRP reinforcing bars in concrete elements in Canadian jurisdictions. I’m seeking the value and where it comes from (I.e. A23.3 or otherwise). Thanks in advance.
  2. pbc825

    Charpy V-Notch Testing Heat Affected Zone

    I've received a specification from a client asking for CVN testing of the heat affected zone. The parent material is 350WT category 1. By my thinking, if the parent material passes CVN (by definition of the material specification) and the weld has as-welded properties that are tough, then the...
  3. pbc825

    Corrosion in underground piping

    We're in a project to assess the condition of a groundwater piping system following observation of leaking in a line in a building. We've identified it's likely occurring by the microbiologically influenced corrosion (MIC) mechanism, which corroded an 8" sch 40 line (0.322" wall) through in a...
  4. pbc825

    Innovative ideas for underground tunnel repair

    I'm working on a project for a mining operator. They have a reinforced concrete tunnel under a product storage structure, and the tunnel is highly chloride impregnated. Replacement in-kind of the tunnel is an option, but the price tag is rather high and indirect costs from lost production make...
  5. pbc825

    Repair recommendations for building with shallow footings experiencing subsidence

    I've been contacted to provide some repair recommendations for a building which has experienced shallow footing subsidence caused by an adjacent sub-grade parking structure excavation. The adjacent lot was excavated and the excavation walls were temporarily supported using anchors and...
  6. pbc825

    Partial Development of Pile Cap Longitudinal Bars for Post-Installed Anchors

    I received a call from site, and the cast-in-place anchors I've designed and detailed were embedded too far into a pile cap. The result is we're cutting and abandoning the four cast-in-place anchors (unweldable) in favour of post-installed bars installed using epoxy. The cast-in-place anchors...
  7. pbc825

    Stainless Steel minimum bottom course thickness

    I'm working on an API 650 tank being fabricated from A240-316L plate with 18' diameter. Design thickness of the bottom course is 0.0835" and API clause 5.6.1.1 recommends a minimum shell thickness of 1/4" for the first course and 3/16" for the upper courses. Appendix S does not note minimum...
  8. pbc825

    Hydrotest in a freshly welded water tank

    We've been retained to provide repair recommendations for an elevated water tank. The tank froze as a result of a water recirculation system failure in the dead of a cold Canadian winter. Large crack. I'm a structural engineer and I've done a number of water tower repairs, assessments and...
  9. pbc825

    Explosion Venting Wall Load Interactions with Bulk Materials

    I'm not sure if this is the right forum to be posting, but I think this is as close as I'm going to come. I'm working on a material estimate for several bins which require explosion venting as they store food products. The bins hold aggregate materials with reasonably large particle sizes...
  10. pbc825

    API 2000 Emergency Venting for Water Storage

    I'm designing an API 650 tank and the governing venting requirements are from API 2000. There are a number of venting requirements from API 2000 (liquid from pumps, thermal, and emergency), but the one I have a question about it emergency venting. If the contents of the tank are not...
  11. pbc825

    Shear Lag in CSA S16

    Good day. I'm designing a connection for which I believe shear lag may be relevant. In this case, the supported beam is subject to both shear and axial force. So I've got a web stiffener welded onto the supporting beam so as to transfer the axial load to the flanges of the supporting beam...
  12. pbc825

    Auger Boring Thrust Force and Drag Estimation

    I’ve been approached by a contrator to provide structural engineering services for an auger boring project. The project has been awarded and the prime contractor has asked the contractor to confirm the pipe size and grade is suitable for installation. Long term performance and operation is out...
  13. pbc825

    Follow up to CSA S6 Bridge Deflection Criteria Thread

    Hello all, I previously made this post http://www.eng-tips.com/viewthread.cfm?qid=426751 It was related to what the deflection limits on a single span bridge girder were in accordance with CSA S6. I've since done some calculations and have a follow-up question regarding CSA S6 deflection...
  14. pbc825

    Fees for piles, grade beams and slabs-on-grade for large construction project

    I've designed a number of piles, grade beams and slabs-on grade in the past. Typically they're for projects that are smaller and our rate/fee schedule is time based. We're quoting on a large construction project, and I'm wondering if there is any advice on a fee schedule based on some...
  15. pbc825

    Uplift on Slab-On-Grade

    Here's a doozie. If I place an anchor bolt in a slab-on-grade concrete floor (let's call it somewhere between 4" and 6") with unknown reinforcing steel layout (often the reinforcing steel is laying flat on the ground in SOG's), would you assume the defining capacity is the concrete cone that...
  16. pbc825

    Longevity of concrete material

    I’ve got a good question for everyone. How long does concrete last? The context of the question is long-term mine opening closures. We’re contracted to close mine openings for a governmental regulator. We’re currently designing them to last a LONG time with stainless steel. They’re not...
  17. pbc825

    Bolts Loosening in Transport

    I just received a phone call from a client who had a lifting/tailing beam nut loosen in transport. The part being transported is a cylindrical shell of ~24' diameter and length. The shell has lifting lugs on top and a tailing beam on the bottom. The tailing beam is left on for transport and...
  18. pbc825

    17-4 stainless wheel rolling on 316 stainless flat bar

    Howdy folks, I'm working on a project that has a 16" diameter stainless steel wheel which I'm proposing to fabricate from 17-4 stainless rolling on a 316 stainless steel flat bar. Wheel loads are in the 45kN range. Client has raised the question of galling. Can anyone provide insight on this...
  19. pbc825

    Deflection Limits for Bridges

    Hello bridge engineers, I've been asked to design a bridge for a client who makes temporary bridges. The client had another engineer making drawings for him, and I've been provided with a sample drawing. These bridges are very basic and are composed of longitudinal beams with a lumber deck...
  20. pbc825

    Lattice Spacing and Angle for Built-Up Sections in CSA S16

    I've taken on a design review for an old (pre 1970's) lattice bridge in an industrial complex with angle chords (2 top and 2 bottom) and lattice members. The top two chords are in compression and act as a built-up member. The scope includes reviewing the bridge in the context of the current...

Part and Inventory Search