We have an elevated tennis court, 6 years old, constructed of 2" metal deck with 4" total thickness of concrete. There is severe ASR finish damage. We want to resurface the concrete by removing +/-1 inch of concrete and replacing with a fully bonded concrete finish. Our concern is the ASR will...