Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  • Users: JXWu
  • Content: Threads
  • Order by date
  1. JXWu

    ASME Section VIII Div. 2 - Internal Piping

    Dear experts, I am working on a spherical pressure vessel constructed to ASME VIII Div. 2. Min. Design metal temp. is -45°C. There are several nozzles at the top of the vessel. One of them is a nozzle for a level transmitter with a stilling well that goes into the vessel. My question is: do the...
  2. JXWu

    ASME IX PWHT Cycles

    Good afternoon. Reference: ASME Section IX and API 650 Welding Process: SMAW My client required the PQR to be qualified with a minimum of 3 PWHT cycles. The material to be welded is 25 mm thick and the PWHT holding is 1 hour. So I PWHT the PQR coupon for 6 hours in one heat. That is, heating...
  3. JXWu

    API 650 Two-Side Welding

    Dear experts, Is it a API 650 requirement that the second side of a double-side welded joint needs to be back-chipped at least one-third of the joint thickness? I cannot find this requirement in the API 650 12th edition. Need advice. Thanks
  4. JXWu

    API 650 Shell Vertical

    Dear experts, API 650 storage tanks My welding process is FCAW-G. On the shell vertical seams, I am considering a single-vee joint, single side welding with ceramic backing. Another option is single-vee, double side welding, which means I need to backgouge the second side. I need advice on...
  5. JXWu

    ASME Section IX QW-403.9

    Dear experts, I need some help with QW 403.9 requirement. I have attached a sketch of my PQR joint detail and production joint detail. My PQR is qualified on 27mm thickness plate welded with a single pass EGW. The production weld is a double vee joint to be welded with a single pass EGW on side...
  6. JXWu

    Welding Lap Joints

    Dear experts, I am working on a storage tank and the project spec. calls for minimum 2 passes welding on the bottom lap joints. Bottom plates is 8mm thick. I am considering using SAW with auto downflat tractor but not sure if it is problem trying put 2 passes in a 8mm lap joint. Please advise...
  7. JXWu

    API 650 Material Grouping Table 4.4a

    In Table 4.4a, A36M is grouped under I and II. Note 3 for Group I A36M says "Thickness ≤ 20 mm." Note 5 for Group II A36M says "...... Thicknesses ≤ 20 mm shall have a manganese content of 0.80 % to 1.20 % by heat analysis. My question is; does the requirement in note 5 applies to note 3 if my...
  8. JXWu

    ASME BPVC.I-2017: PW-40.3

    I found a weld defect on P-No. 1 material after it has been PWHT'ed. I intend to repair the weld followed by another cycle PWHT. NDE will be same as original weld. Question: Does the requirement of section PW-40.3, PW-40.3.1-9 applies if I were to PWHT the repaired weld? My understanding of...
  9. JXWu

    Incoloy 800H (UNS 8810) PWHT

    Hi, I fabricated 800H pipe welded with Inco 82 filler, performed stabilising annealing at 985 deg C for 3 hours. Specified code is B31.3 and the service temperature is 850 deg C. Client specifies a maximum cooling rate of 150 deg C/hr but we exceed this cooling rate. Actual cooling rate is 180...
  10. JXWu

    Pipe Size

    I am looking for a clear definition of "Heavy Wall". Can I say that if the wall thickness is greater than schedule STD for that size, will be considered heavy-wall. Is there a formula which takes diameter and wall thickness into account to determined if a pipe is considered heavy wall. Thanks.
  11. JXWu

    Stabilize annealing 347H Stainless steel

    After welding 347H pipe, we performed stabilizing annealing at 900°C for 4 hours followed by rapid cool with forced air. Our client wants us to perform a hardness test but I do not think it is necessary because the stabilizing annealing is performed to improved the corrosion resistance and not...

Part and Inventory Search