Hello -
I have a footing design requirement for a mezzanine (very long spans), that is calling for 3000 psi with 7 days cure before dead load and 28 days before live load. The engineer is on vacation now. I can't afford to wait the 28 days, so was trying to find out how long it would take 4000...