Hello,
Some capital projects asks for design reviews in 30%, 60%, 90&, 100% while others asks for 50% and 100% only.
what is the difference and when we follow option 1 and when is 2?
thank you
Hello,
I am looking for reports, or schedules which describe all the info and codes, tests required to install all finishes and how to supervise it
ex: Epoxy: need to be mixed with water not more than 2 hours, where to put, how? recycle content, free VOC & formaldehyde
Wooden cabinets: need to...
Dear All,
As I am a beginner, I wish to guide me see how any projects constructor step by step, hope by images or video.
I am looking forward to see all details on site, like pouring concrete, mock-up tests, rebar coupled, concrete casting, slab installing and further more .
Any recommendations?
Dear all,
I am new engineer in company, we are the client or the owner for a project, so we are manage the construction with contractor,
I am an architect with little experience, I need to do a work which realy be appreciated and shown.
My scope now to review subbmittals, modify some work...
Hello,
I got shop drawings subimttal for the Lapeyre stairs attached with the original specs as providing the stair manufacturers, specs, material.
The drawings it self is correct but they did not attach the manufacture, quantities, or any specs for the material the chose.
They mentioned in the...
Hello,
I got shop drawings subimttal for the Lapeyre stairs attached with the original specs as providing the stair manufacturers, specs, material.
The drawings it self is correct but they did not attach the manufacture, quantities, or any specs for the material the chose.
They mentioned in the...
Hello,
This is the first time for me to review submittals, Architecture
Wee have to review two submittal one for mezzanine composite plan, now i am looking in the IFC and Shop drawings, what I supposed to catch if there is any comments?
The other one to review for the roof composite plan...