Hi Forum,
I am dealing with a supplier that will be providing a dry packaged mix and should be upholding the standard on the subject. The ASTM specifies testing for each batch (6 cylinders; 3-7days, 3-28 days); however they do not provide this data for us. For quality control, per contract...
Hi Forum,
My supplier is handing me Mill Certs that conforms to ASTM 529 (carbon-manganese steel)for anchor bolts which should be fabricated and tested under ASTM F1554. I have both the ASTMs and it appears to me that F1554 has stringent quality manufacturing requirements than 529. There is not...