  1. GD2

    Flexibility and Seismic analysis - Piping system

    Experts, Many of you do flexibility analysis of a piping system (say ASME B31.3). Has anyone experience in doing a seismic analysis of the same piping system? There could be instances when you have done the flexibility analysis nut a third party contractor does the seismic analysis. In this...
  2. GD2

    GROUP NO -ASME Sec IX of BPVC

    Can someone define what are Group No 1, 2 and 3 that is subset of P-Nos? I am aware that the Group numbers are assigned when WPS requires impact testing. But what is actually the difference between Gr 1, Gr 2 and Gr 3 and where is it described in ASME BPVC? GDD Canada
  3. GD2

    ON/OFF Valve for Refinery FCC Column Bottom Slurry Service

    Does anyone has any experience with the pneumatic actuated ON/OFF valve for the refinery FCC Column bottom slurry service? Fluid handled: 1) CLO (Clarified Oil from main column bottom with VGO and residue) 2) Slurry content – Solid concentration – 132100 ppmw (solids are FCC catalyst, silica...
  4. GD2

    Fire Protection System UL/FM approved Butterfly/Gate Valves

    Dear Colleagues, I am having a toughtime getting suppliers for UL/FM approved Al-Bronze large sizes valves (around 16 inch size). Can someone help me on this? GDD Canada
  5. GD2

    Spiral weld versus longitudinal and circumferential weld

    Folks, A customer specified a 64 in SS 304 pipe spiral welded. The manufacturer manufactured the pipe with midsection longitudinal seam welded and two end sections with circumferential welds. Should the customer accept or reject the pipe? In terms of spiral weld pipes, what is the usual RT...
  6. GD2

    API 579 FFS on disbonded clad

    Dear friends, Do anyone have experience in FFS assessment of the SS cladding on Low alloy steel base? The vessel is a Reactor in hydro processing unit. The clad has disbonded at few locations. API 579 does not provide any direction on clad assessment. GDD Canada
  7. GD2

    DROPS Inspection/Survey

    Dear Forum members, Does anyone knows of a company who can provide a "DROPS Inspection/Survey" service for a process plant? GDD Canada
  8. GD2

    Pipeline Magnetic Tomography Survey

    Dear members, I am looking to find a company who provides above ground Magnetic Tomography Survey for a buried Transmission Pipeline. Can you suggest some company who provides the service? GDD Canada
  9. GD2

    Overlayed Flanges Cracking under Hydrogen Service

    Dear Members, I have a situation where the root of the groove of the Class 2500 overlayed flanges is cracking under hydrogen gas service. The propagation of cracks in the base metal in some cases are more than 4 inches. Have anyone faced similar problem and the possible remedial action taken for...
  10. GD2

    Electronic Measuring Device for Valve Face-to-face distance in a gas plant

    Dear Members, I was wondering if you know of any Ex rated electronic measuring device for valve Face-to-Face/end-to-end distance in a oil and gas plant? Appreciate your help. GDD Canada