In Wisconsin, the DNR requires post-construction peak discharge at or below the predevelopment 100-yr, 10-yr, and 2-yr, 24-hr frequency storm events. I'm currently working in a municipality that has a more restrictive ordinance, that the 100-year post-development runoff event must be stored and...