    Accounting for Rework in Production Schedule

    I have a very small volume, high complexity, long cycle time product. A typical build takes roughly 6 months. There are test points in the build process with low yields and long rework cycles. I'm trying to account for those failures/reworks in my production plan. Here is my current approach...